Key Information…
Project delivered within programme, within contract sum, zero incidents and BREEAM targets achieved.
Core services provided…
Downtakings
Asset Recovery
Kinetic Demolition were appointed as Principal Contractor to carry out the internal strip out of a four storey building in the busy residential area of Stockbridge in Edinburgh. The project had a very tight timescale of 16weeks given the floor area to be stripped of approximately 20000m2 not including the roof services. The building was sandwiched between a school, residential properties and the busy Brandon Street. Given the requirements of the client the works also involved keeping internal lifts and smoke extract equipment in service during the project.